What Happens After You Sign an App Development Contract?
By Paul Graf ·
You’ve done your research, chosen a developer, signed the contract, and sent the deposit. Now comes the part that surprises most first-time app owners: a lot happens before anyone writes a single line of code.
Here’s what the development process actually looks like, from your first kickoff meeting to the day the app goes live.
Phase 1: Kickoff and Discovery (Week 1–3)
The first meeting after signing is usually called a kickoff. Its purpose is to get everyone aligned on what’s being built, who’s responsible for what, and how you’ll communicate throughout the project.
Your developer will ask you a lot of questions in this phase — questions that might feel tediously detailed when you just want to start building. Answer them thoroughly. The more clearly your developer understands your business, your users, and your goals, the better decisions they’ll make when you’re not in the room.
The discovery phase produces a detailed scope of work document listing every feature and functionality in the project. Review this document carefully before it becomes the official baseline. Anything that’s not in the scope is not included in the price.
Phase 2: Design (Week 2–8, Often Overlapping)
Design usually starts while discovery is being finalized. It happens in two stages:
Wireframes are structural blueprints of your app — simple, black-and-white sketches showing where everything goes on each screen. No colors, no polished visuals, just structure. Wireframes let you give feedback on the layout and user flow before anyone spends time on visual design.
UI design (mockups) takes the approved wireframes and applies the visual layer: colors, typography, icons, images, and brand elements. This is what your app will actually look like.
Expect at least two rounds of revision at each stage. Try to give complete, consolidated feedback rather than piecemeal comments — it’s more efficient for everyone.
Phase 3: Development (Week 4–20+, The Long Middle)
This is where your app gets built. Development typically has two tracks running in parallel:
Front-end development: Building every screen, button, interaction, and animation that users will see and touch.
Back-end development: Building the server, database, and business logic that powers everything behind the scenes — user authentication, data storage, payment processing, notifications.
During development, you’ll typically have check-ins every week or two where your developer shares progress. You may be able to see early builds in TestFlight before all the features are complete. Give feedback as you go, but understand that some things might look incomplete — that’s normal for a build that’s still in progress.
Phase 4: Client Review and Revision (Ongoing)
Throughout development, your developer will ask you to review and approve things: designs, features, content, behavior. This is your active role in the project.
Respond to these requests promptly. Every week of delay on your end is a week added to your timeline. When giving feedback, be specific: “The button should be green” is better than “I don’t like this.” “This flow is confusing — can we add a confirmation screen before the final step?” is more useful than “this doesn’t feel right.”
Phase 5: Testing (Week 16–24, Before Launch)
Before your app launches, it goes through a dedicated testing phase. This involves:
Developer testing (QA): Your developer systematically tests every feature on multiple devices and iOS/Android versions, looking for bugs, edge cases, and performance issues.
Client testing (you): This is where TestFlight comes in. You’ll install the app and use it as a real customer would — testing all the main flows, trying to break things, and giving detailed feedback on anything that seems wrong or confusing.
User acceptance testing (sometimes): A small group of your actual target users tests the app and gives feedback. This is particularly valuable for catching usability issues that the developer and client can’t see because they’re too close to the project.
Phase 6: Launch Preparation (Week 22–26)
While testing is wrapping up, launch preparation happens:
- App Store listing materials (screenshots, description, keywords)
- Privacy policy and terms of service
- Developer account setup
- Final App Store submission
- Apple’s review process (1–3 days)
This phase can take longer than expected if there are App Store rejections (common with first-time submissions) or if listing materials need revision.
Phase 7: Launch Day
When Apple approves the app, it goes live. For most small business apps, launch is less of a dramatic moment and more of a quiet milestone — the app is now available, and now the real work of getting users begins.
Your developer’s role in the project is largely complete at this point, though most include a 30–90 day warranty period for bug fixes that surface after launch.
What Comes Next: Post-Launch
The first month after launch is a learning period. You’ll see how real users interact with the app, what questions come up, what features they love, and what’s confusing. Collect this feedback systematically — it’s the input for your first update.
Budget for ongoing maintenance. iOS and Android release major updates once or twice a year, and your app will need work to stay compatible and continue running smoothly.
Frequently Asked Questions
How involved do I need to be during development? More than most clients expect. You’ll be asked to review and approve designs, content, and features — sometimes on a weekly basis. The projects that go smoothly are the ones where the client is engaged and responsive. Delays on the client side are one of the most common causes of projects running over schedule.
What if I change my mind about a feature mid-development? Changes during development are common and possible, but they have a cost. Any feature or change that wasn’t in the original scope will typically require a change order — a small contract that defines the additional work and price. This is fair and expected. The key is to make changes deliberately, knowing they affect timeline and budget.
When does the developer get paid during the project? Typically in milestones: a deposit at contract signing (usually 25–30%), one or more milestone payments tied to deliverables (design approval, development completion), and a final payment when the project is complete to your satisfaction. This structure protects both parties.
Have questions about your specific project? Graf x Apps offers free consultations — no pressure, just honest advice. Contact us here